Jacksonville's Next Interstate: I-795
Progress continues on the construction of Jacksonville's next interstate. Here's an update on the project's status.
State Road 9B (SR 9B) is a planned four lane divided highway that will eventually connect Duval and St. Johns County from the I-295 East Beltway to County Road 2209 (St. Johns Parkway).The corridor is divided into three phases. Construction on Phase 1 began in summer 2010 and the $75 million phase opened to traffic in September 2013.
Construction began on Phase 2, from Interstate 95 to US 1/Philips Highway, in April 2013. As a part of this $95 million phase, a massive interchange with Interstate 95 is being constructed. Beam setting over Interstate 95 is currently in progress. Phase 2 is expected to open to traffic in mid 2016.
The last phase of SR 9B will begin west of I-95 and extend approximately 1.5 miles south, where it will connect with County Road 2209 (St. Johns Parkway). Phase 3 is anticipated to cost $79.8 million, construction will begin fall 2015, and it is expected to be completed by Mid 2018.
It is anticipated that the completion of SR 9B will result in a major real estate development boom along the Duval County/St. Johns County border. A brief description of major developments lining up along the SR 9B corridor can be found HERE.
When complete, SR 9B is anticipated to become I-795. I-795 will be Jacksonville's fourth and St. Johns County's second interstate highway.
![](https://photos.metrojacksonville.com/photos/4132485032_GKF6mqP-800x2000.jpg)
For more information: https://www.sr9b.com/Pages/Home.aspx
Next Page: Images of the SR 9B construction project
1.
![](https://photos.metrojacksonville.com/photos/4112632896_pwgjmHc-L.jpg)
2.
![](https://photos.metrojacksonville.com/photos/4112633127_MP4M9xR-L.jpg)
3.
![](https://photos.metrojacksonville.com/photos/4112633772_3cNMrMJ-L.jpg)
4.
![](https://photos.metrojacksonville.com/photos/4112667282_8SvLPPJ-L.jpg)
5.
![](https://photos.metrojacksonville.com/photos/4112667652_V7MhjTD-L.jpg)
6.
![](https://photos.metrojacksonville.com/photos/4112667666_ZXm3Zsx-L.jpg)
7.
![](https://photos.metrojacksonville.com/photos/4112667697_k2954TV-L.jpg)
8.
![](https://photos.metrojacksonville.com/photos/4112668125_TKhG8vd-L.jpg)
9.
![](https://photos.metrojacksonville.com/photos/4112668107_Mz2JQtJ-L.jpg)
10.
![](https://photos.metrojacksonville.com/photos/4112668478_K543ZxV-L.jpg)
11.
![](https://photos.metrojacksonville.com/photos/4112668539_tD2M4Gv-L.jpg)
12.
![](https://photos.metrojacksonville.com/photos/4112668490_ZB9Cztg-L.jpg)
13.
![](https://photos.metrojacksonville.com/photos/4112666867_x2nbGjW-L.jpg)
14.
![](https://photos.metrojacksonville.com/photos/4112666860_2mZdh5Q-L.jpg)
15.
![](https://photos.metrojacksonville.com/photos/4112666803_PPcLvZq-L.jpg)
16.
![](https://photos.metrojacksonville.com/photos/4112667073_p6PhVt2-L.jpg)
17.
![](https://photos.metrojacksonville.com/photos/4112667235_Z96RFKf-L.jpg)
18.
![](https://photos.metrojacksonville.com/photos/4112667237_KdpJ6N9-L.jpg)
Update and images by Ennis Davis, AICP. Contact Ennis at edavis@moderncities.com
Construction began on Phase 2, from Interstate 95 to US 1/Philips Highway, in April 2013. As a part of this $95 million phase, a massive interchange with Interstate 95 is being constructed. Beam setting over Interstate 95 is currently in progress. Phase 2 is expected to open to traffic in mid 2016.
The last phase of SR 9B will begin west of I-95 and extend approximately 1.5 miles south, where it will connect with County Road 2209 (St. Johns Parkway). Phase 3 is anticipated to cost $79.8 million, construction will begin fall 2015, and it is expected to be completed by Mid 2018.
It is anticipated that the completion of SR 9B will result in a major real estate development boom along the Duval County/St. Johns County border. A brief description of major developments lining up along the SR 9B corridor can be found HERE.
When complete, SR 9B is anticipated to become I-795. I-795 will be Jacksonville's fourth and St. Johns County's second interstate highway.
![](https://photos.metrojacksonville.com/photos/4132485032_GKF6mqP-800x2000.jpg)
For more information: https://www.sr9b.com/Pages/Home.aspx
Next Page: Images of the SR 9B construction project
1.
![](https://photos.metrojacksonville.com/photos/4112632896_pwgjmHc-L.jpg)
2.
![](https://photos.metrojacksonville.com/photos/4112633127_MP4M9xR-L.jpg)
3.
![](https://photos.metrojacksonville.com/photos/4112633772_3cNMrMJ-L.jpg)
4.
![](https://photos.metrojacksonville.com/photos/4112667282_8SvLPPJ-L.jpg)
5.
![](https://photos.metrojacksonville.com/photos/4112667652_V7MhjTD-L.jpg)
6.
![](https://photos.metrojacksonville.com/photos/4112667666_ZXm3Zsx-L.jpg)
7.
![](https://photos.metrojacksonville.com/photos/4112667697_k2954TV-L.jpg)
8.
![](https://photos.metrojacksonville.com/photos/4112668125_TKhG8vd-L.jpg)
9.
![](https://photos.metrojacksonville.com/photos/4112668107_Mz2JQtJ-L.jpg)
10.
![](https://photos.metrojacksonville.com/photos/4112668478_K543ZxV-L.jpg)
11.
![](https://photos.metrojacksonville.com/photos/4112668539_tD2M4Gv-L.jpg)
12.
![](https://photos.metrojacksonville.com/photos/4112668490_ZB9Cztg-L.jpg)
13.
![](https://photos.metrojacksonville.com/photos/4112666867_x2nbGjW-L.jpg)
14.
![](https://photos.metrojacksonville.com/photos/4112666860_2mZdh5Q-L.jpg)
15.
![](https://photos.metrojacksonville.com/photos/4112666803_PPcLvZq-L.jpg)
16.
![](https://photos.metrojacksonville.com/photos/4112667073_p6PhVt2-L.jpg)
17.
![](https://photos.metrojacksonville.com/photos/4112667235_Z96RFKf-L.jpg)
18.
![](https://photos.metrojacksonville.com/photos/4112667237_KdpJ6N9-L.jpg)
Update and images by Ennis Davis, AICP. Contact Ennis at edavis@moderncities.com