Jacksonville Transportation Center moves forward
Although the city continues to fail to address the convention center's future, JTA appears to be moving forward with plans for the construction of a new transportation center. Today, Metro Jacksonville shares renderings of what the center will look like once completed.
![](https://photos.metrojacksonville.com/photos/719079450_mYBba-M.jpg)
This rendering shows the view of the transportation center, looking west from Johnson Street. To make the open plaza seem more inviting, the consideration of retail/dining on the plaza itself should be evaluated.
A local example of this would be Riverside Square in Five Points.
![](https://photos.metrojacksonville.com/photos/633081563_pseSu-M.jpg)
JTA's proposed office building, looking north across Bay Street, from the Prime Osborn's parking lot. An opportunity to stray away from solid walls at street level seems to have been wasted.
![](https://photos.metrojacksonville.com/photos/719079357_KNDZy-M.jpg)
Another view of the office building and transportation center, looking east along Bay Street.
![](https://photos.metrojacksonville.com/photos/719079372_NUrM4-M.jpg)
A view of the office building and transportation center looking east along Forsyth Street.
![](https://photos.metrojacksonville.com/photos/719079391_KzaC6-M.jpg)
An aerial of the proposed transportation center, which will be just north of the Prime Osborn convention center.
![](https://photos.metrojacksonville.com/photos/719079408_PsyLT-M.jpg)
A sketch of the transportation center's public plaza, looking west from Johnson Street.
![](https://photos.metrojacksonville.com/photos/719079435_HpdSu-M.jpg)
An aerial of the Jacksonville Transportation Center at buildout.
![](https://photos.metrojacksonville.com/photos/494587132_xXYYH-M.jpg)
Phase 1 Statistics
Bus Rapid Transit Stations
Greyhound Bus Station
200 parking spaces
8,000 square feet of retail space on Johnson and Forsyth
Public Plaza facing Johnson Street
4-story, 60,000 square foot transportation office building
Future Phases
Amtrak/commuter rail station
Renovation of Prime Osborn to make it a part of rail station when conventions aren't occuring
An Elevated, 2,000-space parking garage
Estimated Costs
Total Cost: $180 million
Money spent to date: $10 million (design and environmental studies)
Federal stimulus request: $63 million
Construction Date
Late 2010, assuming JTA is awarded $63 million in federal stimulus funds this Winter. To date, the U.S. Department of Transportation has received 1,400 applications totaling $57 billion from every state for the $1.5 billion stimulus allocation.
Source: Jacksonville Transportation Authority
https://jacksonville.com/news/metro/2009-11-11/story/stimulus_funds_sought_for_transportation_center_in_jacksonville
Article by Ennis Davis